Value Delivered
Our team provided professional installation of a new, cutting-edge cooling system at Denver Public Schools’ Rishel Junior High. All work was completed over two summers, in order to avoid impacting the students and teachers during the school year.
Client Objectives
The client wanted a new, more efficient cooling system and needed a mechanical contractor that could work around their school schedule.
Solutions
Complete cooling system installation, including mechanical and electrical systems, for:
- Six indoor air handling units
- Six packaged rooftop units
- One air-cooled chiller
- Four variable air volume (VAV) boxes
- One chilled water pump